Our projects

Intu Shopping Centre, Watford

We carried out the survey of the rotunda, then  detailed and erected the hot-rolled steel mullions to  take the cladding to the perimeter which had to be  within tolerances of 3 to 5 mm.

This proved challenging as the concrete was out  considerably and we had to in-build a certain amount  of tolerance within the design of the brackets to take  the steel mullions.

Performing Arts Block, Wellington College

Being a circular structure, the detailing of the new Performing Arts Block with a  clear span was a challenge as the margin for error had been reduced considerably.

All the holding down bolts were resin anchors set  out and installed by Advanced Fabrications Poyle  Limited. The pre-cast terrace units sat on raking steel  members which had to be installed prior to the roof  structure being fitted therefore we had to ensure  that the columns would not move to allow the roof to fit.